| Location |
Hastings Park Drive to Champagne Drive |
| Project Estimate |
$832,697 |
| Extent of Work |
- Replacement of existing watermain with a larger 300mm diameter pipe
|
| Details |
Environmental Services has identified the replacement of the watermain as a top priority due to discoloured water problems. The pipe diameter is to be increased from the existing 150mm to 300mm as identified in the Loyalist Secondary Plan Area Water Distribution System Study. This will facilitate future growth in this area. Full reinstatement of the road from Monteagle Blvd. and Champagne Dr. will also be done to correct deficiencies in the existing asphalt road surface. |
| Commencing |
Awarded to North Key Construction on July 11, 2011. Work began on August 2nd |
| Complete |
Fall 2011 |
| Progress |
This project was completed in November 2011 |


Avonlough Road after completion, November 2011