| Location |
Intersection at College St. E. and Cannifton Rd. Parkway |
| Project Estimate |
$1.36M |
| Extent of Work |
- Construction of a dedicated westbound right turn lane
- Extension of the westbound left turn lane
- Reconstruction of the traffic signals to allow for concurrent left turns.
- Addition of pedestrian crosswalks to all quadrants of the intersection with audible signals
- Impressed concrete to be placed for the existing and new traffic islands, as well as certain boulevard areas.
- Resurfacing of the intersection
- Resurfacing of Cannifton Rd. Pkwy from College St. E. to Station St.
|
| Commencing |
Awarded to Coco Paving Inc. on August 8, 2011. Work to begin summer 2011 |
| Complete |
Fall 2011 |
|
Intersection work progress October 7/11 |
|
 |
|
Intersection work progress October 7/11 |

Intersection Progress November 24/2011